Applying our Steam Generators Replacement skills in Brazil
Eletronuclear prepared Angra 1 Steam Generator Replacement call for tender documents (technical and contractual specifications) with Tractebel Engineering support (under Belgatom name).
2002 - 2005
Brazil
Coyne et Bellier continuously assists EDF experts teams
Various specialised civil works related studies in the framework of existing NPPs operational support and life extension for all EDF NPP type (P4, P'4, N4, CP1/CP0).
1998 - ongoing
France
LEME wins its first nuclear contract in Brazil
Eletronuclear will benefit during 19 months from Leme's engineering services in support of plant operation for its PWR plant Angra 1 (657 MW) and Angra 2 (1350 MW).
2005 - 2007
Brazil
Modifications at Borssele NPP
Together with GTI we are performing for EPZ at Borssele NPP ten-year Safety Reassessment related modifications. The project comprises the engineering and carrying out of various improvements that have to made following the ten-yearly safety reassessment.
2004 - 2007
Netherlands
On-Site Assistance for South Ukraine NPP
After obtaining a one year contract in March 2004 for the « On-Site Assistance » services at the nuclear plant of South Ukraine, the good performance of the Tractebel Engineering / Electrabel consortium has just been confirmed in December 2004. The consortium won an assistance contract in the same nuclear plant for duration of an extra three years.
2005 - ongoing
Ukraine
Refurbishment of the internal structures of the Tihange 3 cooling tower
Abnormal failures of the internal supporting concrete structure in the cooling tower of Tihange 3 lead to an overload of the clogged packing and a concrete structure presenting lacks in design, resistance and durability. Electrabel entrusted Tractebel Engineering with an extended analysis of structure and decided to replace the clogged packing and, for the 1st time in the world, the supporting concrete beams. After additional studies, the site works were completed 2 days ahead of schedule. Thanks to a strict organisation, the Zero Significant Accident Target was met.
2005 - 2006
Belgium
Safety Reassessment programs
Since the connection to the grid of the Belgian nuclear power plants, we are applying our global and integrated approach leading to cost efficient proposals for ten-yearly safety improvements of Electrabel nuclear power plants.
1985 - ongoing
Belgium
Steam Generator Replacement Management
Electrabel entrusts us since 1993 for the successive management of 6 Steam Generator Replacement in a multi-contract approach, leading to an efficient contracting policy. SGR Doel 2 was performed in 2004 with a significant power increase in 15 days during a 65 days outage and a SG dosimetry limited to 195 man.mSv .
1993 - 2004
Belgium
Support for In-Service Inspection qualification at Koeberg NPP
Tractebel Engineering seconds ESKOM's Koeberg NPP with a senior ISI qualification expert to set-up requirements, provide technical support and evaluation, high-level overview and optimise interaction with Safety Authorities.